ANALISIS FAKTOR PENYEBAB KETERLAMBATAN PELAKSANAAN PROYEK REHABILITASI SEKOLAH DALAM MASA PANDEMI COVID-19

  • Gusni Vitri Universitas Dharma Andalas
  • Wendi Boy Universitas Dharma Andalas
  • Wiwin Putri Zayu Universitas Dharma Andalas

Abstract

Implementation of construction projects requires resources of materials, labors, equipments, methods and capital to achieve project objectives, namely on time, on quality and according to planned costs. Various internal and external factors influence during project implementation. The conditions of the Covid-19 pandemic that occurred in Indonesia and the world were one of the factors inhibiting project completion. The Primary School Rehabilitation Project in West Pasaman Regency is spread over 15 (fifteen) locations in all sub-districts. The project was contracted in early 2020, before the Covid-19 outbreak erupted. This project has been delayed due to the implementation with 2 (two) addendums to extend the implementation time. This research is descriptive quantitative and qualitative, with data collection techniques through questionnaires and direct interviews with respondents, that are Contractor, Construction Management Consultant and Owner (Ministry of Public Works, Housing and Building Information Center Work Unit West Sumatra Province). The results showed that the most dominant cause of project delays was Force Majeure, Government Policy, Design. Apart from that, other factors that also influence are the weather, the characteristics of the place and the materials.

Keywords: Project Delays, Covid-19 Pandemic, School Rehabilitation, Construction Contract

References

Hassan, Haekal. 2016. Faktor-faktor Penyebab Keterlambatan Pada Proyek Konstruksi Dan Alternatif Penyelesaiannya (Studi Kasus: Di Manado Town Square III). Jurnal Sipil Statik Universitas Sam Ratulangi Vol.4 No.11 November 2016.
Khaidir, Indra. 2018. Faktor Penyebab Keterlambatan Pelaksanaan Proyek Konstruksi Di Sumatera Barat. Jurnal Rekayasa Vol. 8, No. 01 tahun 2018.
Messah Y, Widodo T, Adoe M. 2013. Kajian Penyebab Keterlambatan Pelaksanaan Proyek Konstuksi Gedung Di Kota Kupang. Jurnal Teknik Sipil Universitas Kristen Petra, Vol. II, No. 2, September 2013.
Soeharto, Imam, ”Manajemen Proyek Dari Konseptual Sampai Operasional”. Erlangga. Jakarta. 1995.
Sudjana N dan Ibrahim R. 1989. Penelitian dan Penilaian Pendidikan. Sinar Baru Algesindo, Bandung.
Sulaiman M, Munirwansyah, Azmeri. 2017. Analisis Penyebab Keterlambatan Pelaksanaan Proyek Ditinjau Dari Waktu Pelaksanaan Di Provinsi Aceh. Jurnal Ekonomi Transportasi, Manajemen Konstruksi Dan Perencanaan Wilayah vol 1 No. 2 Desember 2017.
Sutan Syah, Mahendra Ir. Manajemen Proyek. Gramedia Pustaka Utama, Jakarta, 2004.
Undang-Undang Jasa Konstruksi No. 2 Tahun 2017.
Waluyo, Rudi. 2014. Kajian faktor penyebab keterlambatan waktu pelaksanaan proyek konstruksi. Jurnal media komunikasi Teknik Sipil Vol. 17, No. 2 Desember 2014.
Yasin, Nazarkhan. 2006. Mengenal Kontrak Konstruksi di Indonesia. PT. Gramedia Pustaka Utama, Jakarta.
Published
2020-12-28
Section
Articles
PDF (Bahasa Indonesia)
Abstract views: 924
downloads: 862