EVALUASI PENERAPAN BUILDING INFORMATION (BIM) 5D TERHADAP WAKTU REVIEW UNTUK OPTIMALISASI WAKTU DAN BIAYA

  • rio hamdani universitas riau

Abstract

RIO HAMDANI, NIM 1410246101. Evaluation of the Implementation of Building Information (BIM) 5D on Review Time For Optimizing Time And Costs, supervised by Sigit Sutikno and Manyuk Fauzi.

 

Design review efficiency to obtain the changes order document is very important to be completed at the beginning of the project and not overlapping to the implementation schedule. One cause of the addendum or CCO is a drawings error that use 2D CAD software suchas mismatches design, design changes, specification changes, design errors and drawings that are less detailed and complete so that it affects the work schedule and material purchases.

This research was conducted using a descriptive qualitative approach where data were obtained from interviews and questionnaires on four competent personnel both from the contractor and construction management consultants to then be compared with data obtained from BIM practitioners.

With this research it is proven that the use of BIM greatly helps the efficiency of review time so that it affects the overall project time achievements. The efficiency of review time can be achieved by 52.94%, the calculation of volume and cost can be improved by 42%. While the cost efficiency and number of personnel are 9% and 9.5%.

 

Keywords: Time, Efficiencies, Reviews, BIM

Keywords: Time, Efficiencies, Reviews, BIM

References

Cinthia Ayu Berlian, 2016, Perbandingan Efisiensi Waktu, Biaya, Dan Sumber Daya Manusia Antara Metode Building Information Modelling (BIM) Dan Konvensional (Studi Kasus: Perencanaan Gedung 20 Lantai), Jurnal Karya Teknik Sipil, Volume 5, Nomor 2, Tahun 2016.
Eastman, C. M., Teicholz, P., Sacks, R., and Liston, K. 2008. BIM Handbook: A Guide To Building Information Modeling For Owners, Managers, Architects, Engineers, Contractors, And Fabricators, Wiley, Hoboken, N.J
Faridi A.S. and El-Sayegh, S.M. (2006). Significant Factors Causing Delay in The UAE Construction Industry. Construction Management and Economics, Vol. 24, p. 1167–1176. Toor,
Jurnal Ilmiah Media Engineering Vol. 2, No. 4, November 2012
Jurnal Prinsip Penulisan Kuesioner Penelitian, Isti Pujihastuti, Desember 2010
Rayendra, Studi Aplikasi Teknologi Building Information Modeling Untuk Pra-Konstruksi, Simposium Nasional RAPI XIII - 2014 FT UMS ISSN 1412-9612 S-14
Soemardi, B.W., (2010). Building Information Modeling: Teknologi Grafis Untuk Pengelolaan Pembangunan Gedung Konstruksi Indonesia. Gagasan Teknologi dan Produk Konsturksi Bernilai Tambah Tinggi Karya Anak Bangsa. Kementerian Pekerjaan Umum
Wisnu Adi Prasetya, 2018, Tinjauan Bim (Building Information Modelling) Dalam Bidang Ict Konstruksi Di Negara ASEAN Seminar Nasional Edusainstek ISBN : 978-602-5614-35-4 FMIPA UNIM
Willem Sapulette. (2009) Analisa Penyebab Dan Pengaruh Change Order Pada Proyek Infrastruktur Dan Bangunan Gedung Di Ambon.