ANALISIS PERCEPATAN DURASI PENYELESAIAN PROYEK KONTRUKSI JALAN MENGGUNAKAN METODE TIME COST TRADE OFF DENGAN PENAMBAHAN JAM KERJA DAN JUMLAH ALAT BERAT

Authors

  • Moh Salman Al farisi Universitas Pembangunan Nasional Veteran Jawa Timur
  • Zetta Rasullia Kamandang Universitas Pembangunan Nasional Veteran Jawa Timur

DOI:

https://doi.org/10.36341/racic.v9i2.4287

Keywords:

Acceleration Analysis, Time Cost Trade off, road

Abstract

Acceleration of the duration of project completion often occurs because it is influenced by several factors which cause the project to be completed before the specified time. The Time Cost Trade Off (TCTO) method is a time and cost comparison method used to shorten the implementation time of construction projects. The X arterial road project which is the case study in this research has completed 35.45% of the work with a percentage of delays that must be caught up at 5.3%. The acceleration analysis in this case study implements the TCTO method with alternative work hours (overtime) and heavy equipment on critical project work to obtain efficient results in terms of time and cost. As a result, it was found that normal labor costs and normal project duration for the remaining critical work were IDR. 802,650,747.00 with a remaining settlement duration of 89 days. Then after acceleration, we obtained an additional 4 hours of overtime work per day and additional heavy equipment with a labor cost of IDR. 278,314,091.00 which can shorten the duration by 56 days. So, based on the results of the analysis, the cost required to accelerate the X arterial road project is Rp. 1,080,964,838.39 with a completion time of 33 days.

Downloads

Download data is not yet available.

References

Z. R. Kamandang and C. B. Casita, “Delays in Construction Project : A Review,†IPTEK J. Proc. Ser., vol. 0, no. 6, 2018, doi: 10.12962/j23546026.y2018i6.4631.

Y. Putra and S. Hartati, “Optimalisasi Waktu Dan Biaya Menggunakan Metode Least Cost Analysis Pada Proyek Peningkatan Jalan Lingkar Kota Dumai,†J. Saintis, vol. Vol. 17 No, no. April, pp. 100–112, 2017.

Kemayotin, “Implementasi IT Project Management Pembuatan Sistem Informasi Senat Mahasiswa (Studi kasus: Fakultas Farmasi Universitas Pancasila),†Seinasi …, pp. 86–93, 2018, [Online]. Available: https://conference.upnvj.ac.id/index.php/seinasikesi/article/viewFile/43/49

N. Khairunnisa, “Analisis Pengendalian Biaya dan Waktu Terhadap Proyek Konstruksi Dengan Metode Earned Value (Studi Kasus: Proyek Perumahan Penajam Paser Utara),†J. Teknol. Sipil, vol. 4, no. 1, pp. 9–19, 2020.

R. Widyo Kisworo, “Analisis Percepatan Proyek Menggunakan Metode Time Cost Trade Off Dengan Penambahan Jam Kerja Lembur Dan Jumlah Alat,†e-Jurnal Matriks Tek. Sipil, no. September 2017, p. 766, 2017.

T. E. Saragi, “Optimasi Waktu Dan Biaya Percepatan Proyek Menggunakan Metode Time Cost Trade Off Dengan Alternatif Penambahan Tenaga Kerja Dan Jam Kerja (Lembur) (Studi Kasus : Pembangunan Gedung Convention Hall Kab. Deli Serdang),†Constr. J. Tek. Sipil, vol. 1, no. 2, pp. 53–69, 2022, [Online]. Available: http://repository.uhn.ac.id/handle/123456789/6146

I. Hendriyani, “Optimasi Waktu dan Biaya pada Pelaksanaan Proyek Peningkatan Jalan Bina Bakti Kelurahan Gunung Seteleng Kabupaten Penajam Paser Utara dengan Metode Time Cost Trade Off (TCTO),†J. Ilm. Tek. Sipil TRANSUKMA, vol. 3, no. 1, pp. 65–76, 2020, doi: 10.36277/transukma.v3i1.72.

E. A. Budianto, “Analisis Optimasi Waktu Dan Biaya Dengan Metode Time Cost Trade Off Pada Proyek Gudang Amunisi.,†J. Apl. Tek. Sipil, vol. 19, no. 3, p. 305, 2021, doi: 10.12962/j2579-891x.v19i3.9146.

I. dan L. Widiasanti, manajemen kontruksi, 1st ed. bandung: PT F5MA"IA ROSDAI(ARYA, 2013.

N. Setiswati, “ANALISIS PRODUKTIVITAS ALAT BERAT PADA PROYEK PEMBANGUNAN PABRIK KRAKATAU POSCO ZONE IV DI CILEGON Dwi,†pp. 91–103, 2013.

W. I. Ervianto, Manajemen Proyek Konstruksi, Revisi. andi, 2005. [Online]. Available: http://katalog.kemdikbud.go.id/index.php?p=show_detail&id=91316

U. Wateno, priyoto, “ANALISIS WAKTU DAN BIAYA DENGAN METODE CRASH DURATION PADA KETERLAMBATAN PROYEK PEMBANGUNAN JEMBATAN SEI HANYU KABUPATEN KAPUAS Wateno,†vol. 6, no. 1, pp. 8–22, 2017.

Published

2024-12-26

Issue

Section

Articles