ANALISIS KETERLAMABATAN DENGAN METODE STOKASTIK DAN MITIGASI RISIKO (Studi Kasus : Proyek Instalasi Pengolahan Air Limbah B1 Kota Pekanbaru)
DOI:
https://doi.org/10.36341/racic.v9i2.4439Keywords:
RII, Risk Mitigation, StokastikAbstract
The issue of environmental pollution has become a strategic issue because of its chain effects on all aspects of life. The construction of the City of Pekanbaru wastewater treatment facility is aimed at the treatment of domestic wastewater due to the density of the population and economic activity so that the quality of the environment is awakened. In this study, the risk of delay in the construction of a sewage treatment facility B1 in Pekanbaru was identified using the Relative Importance Index. (RII). The actual work duration is delayed against the duration of the original plan. Risk analysis uses a stochastic approach to the duration of work. In this analysis, the probability distribution function triangle distribution with 3-point estimate is used. This risk simulation uses @risk software with a maximum of 100,000 iterations. Work in the critical trajectory plays a crucial role in setting the project completion timetable. Initially, the estimated time of execution of the work was 1,075 days. After the analysis (Risk Pert Before Mitigation) the execution time with a 95% confidence rate reached 1,370 days, suggesting a potential delay of 295 days.
Downloads
References
KETERLAMBATAN PADA PROYEK KONSTRUKSI DAN ALTERNATIF PENYELESAIANNYA (STUDI KASUS : DI MANADO TOWN SQUARE III),†J. Sipil Statik, vol. 4, no. 11, pp. 657–664, 2016.
H. Hassan, J. B. Mangare, and P. A. K. Pratasis, “Faktor-Faktor Penyebab Keterlambatan Pada Proyek Konstruksi dan Alternatif Penyelesaiannya (Studi Kasus : Di Manado Town Square III),†J. Sipil Statik, vol. 4, no. 11, pp. 657–664, 2016.
H. Maprilana and K. Koespiadi, “ANALYSIS SCHEDULING PROJECT USING CPM METHOD (Case study : Project of the Surabaya Caspian Tower Apartment),†IJEEIT Int. J. Electr. Eng. Inf. Technol., vol. 2, no. 2, pp. 26–39, 2020, doi: 10.29138/ijeeit.v2i2.1155.
A. Sandhyavitri and dan Reni Suryanita, “Optimasi Kinerja Proyek Pembersihan Crude Oil Contaminated Soil (Cocs) Melalui Mitigasi Risiko Dan Metode Pendekatan Lean Sigma (Studi Kasus Proyek Pembersihan Cocs Di Lokasi 5E-42 Minas),†J. Sains dan Teknol., vol. 14, no. 2, pp. 58–68, 2015.
A. Sandhyavitri, B. Robbani, R. R. Husaini, D. Dianastuti, and B. Istijono, “Risk Analyses for High Voltage Electrical Transmission Projects Based on the Relative Importance Index Method.â€
A. Sandhyavitri, I. Talha, M. Fauzi, and S. Sutikno, “Managing construction risks of the toll road project in Indonesia,†Int. J. Adv. Sci. Eng. Inf. Technol., vol. 7, no. 5, pp. 1934–1942, 2017, doi: 10.18517/ijaseit.7.5.1349.
Downloads
Published
Issue
Section
License
1. Copyright of all journal manuscripts is held by the RACIC : Rab Construction Research
2. Formal legal provisions to access digital articles of electronic journal are subject to the provision of the Creative Commons Attribution-ShareAlike license (CC BY-NC-SA), which means that RACIC : Rab Construction Research is rightful to keep, transfer media/format, manage in the form of databases, maintain, and publish articles.
3. Published manuscripts both printed and electronic are open access for educational, research, and library purposes. Additionally, the editorial board is not responsible for any violations of copyright law.
licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.